Cabot Street Project

View Original

Week of 8/5/19 - 8/9/19

N Granese is currently cleaning and lining the water main with two separate crews between Lenox St and Elliott St. The next phase of the project will be between Elliott St and St. Mary’s. They should be working in these corridors for the next couple of weeks. The next phase, which should begin at the end of August at the earliest, the crew will continue working from St. Mary’s to Bartlett St. A link to that project can be found here.  

City crews are scheduled to begin installing lighting conduit tomorrow (8/8/19) and continue until the entire corridor (Pond St - Abbott St) is complete.

Expect delays and proceed with caution. The City of Beverly puts a high priority on the safety of the construction workers and police officers.