Week of 3/30/20 - 4/10/20

Week of March 30th - April 3rd - City crews will begin to install electrical conduit on the even side on the road between Pond St to Federal St. Trees and parking kiosks will be taken down. Sidewalk contractor may begin to jackhammer in front of the curb line and start to demo the sidewalks.

Week of April 6th - April 10th - City crews will continue to install electrical conduit on the even side on the road between Pond St to Federal St. Sidewalk contractor will continue to set curbing and demo the sidewalks.

Phase 2Sean Ciancarelli