Posts in Archive
Week of 5/28/19 - 5/31/19

NEUCO (National Grid Gas subcontractor) will continue installing the new plastic gas main this week. A second crew has started to help speed up the timeline of the project. One crew will continue installing main around the intersection of Federal Street and towards the limit of work on Abbott St. The second crew will be installing gas main at the intersection of Pond and Knowlton Streets. 

Read More
Week of 5/20/19 - 5/24/19

NEUCO (National Grid Gas subcontractor) will continue installing the new plastic gas main this week. The crew will continue installing main around the intersection of Federal Street and towards the limit of work of Abbott St.  

Read More